SITE PREPARATION REQUIREMENTS FOR CUSTOMERS

 

 

SITE PREPARATION MUST BE ONE OF THE FOLLOWING.

THESE ARE MINIMUM REQUIREMENTS AS DIRECTED BY THE MISSOURI PUBLIC SERVICE COMMISSION (PSC).

CHECK WITH YOUR LOCAL CODES FOR ANY ADDITIONAL REQUIREMENTS.

 

1.     LEVEL ASPHALT PARKING LOT.

2.     LEVEL COMPACTED GRAVEL PARKING LOT.

3.     LEVEL DIRT SITE WITH CONCRETE PIERS POURED IN GROUND TO FROST LINE AND UP TO GRADE.  PIERS TO BE LOCATED PER PLAN PROVIDED TO CUSTOMER BY MISSOURI EQUIPMENT LEASING, INC.

4.     LEVEL DIRT SITE WITH 24” DIAMETER HOLE DUG TO FROST LINE WITH PIER PAD (CONCRETE WITH MINIMUM THICKNESS OF 4” OR ABS PLASTIC) SET IN BOTTOM OF HOLE AND CONCRETE BLOCKS SET IN HOLE UP TO GRADE.  HOLE TO BE BACKFILLED WITH COMPACTED DIRT OR GRAVEL.

5.     LEVEL DIRT SITE MUST HAVE GRASS BLADED OFF AND THEN COVERED WITH 10” OF 3/4”-1” GRAVEL AND COMPACTED WITH A ROLLER.

 

SITE MUST ALSO INCLUDE

 

1.     PLASTIC VAPOR BARRIER MINIMUM 6 MIL THICKNESSES TO BE INSTALLED OVER ENTIRE SITE TO WHICH THE MODULAR UNIT IS TO BE SETTING ON.

2.     GRASS, ROOTS, ETC. IS TO BE REMOVED FROM SITE TO CREATE AN AREA IN WHICH TO INSTALL THE VAPOR BARRIER.